Early works has been taking place including Soldier & Contiguous pile installation, capping beam installation and excavation occurring on site. These works are expected to be complete within the next fortnight after which time hydraulic bracing installation between capping beams will occur which will then allow for the main bulk excavation and shotcreting works to continue.